M6 J6/A38(M) Spaghetti / Gravelly Hill Interchange – Highways England Repair & Re-surfacing works July 2017

Traffic management will be in place during the works, including seven full-weekend closures of junction 6 of the M6, entry and exit slip roads slip roads and the A38(M) into and out of Birmingham.

This is due to start from 7 July 2017 (TBC).

The work will be carried out during the summer months when the road is at its quietest with the M6 itself remaining fully open throughout.

Traffic management restrictions for the duration of the work:

  • The tidal-flow lane on the A38(M) (controlled by electronic overhead signs) will be closed.
  • Narrow lanes on A38(M) with a 30mph speed limit for safety reasons.
  • 24/7 closure of the Gravelly Hill (restrictions from Six Ways) and Tyburn Road approaches to the A38(M) into city carriageway – diversions will be in place.
  • Park Circus on-slip will remain open.
  • Salford Circus will remain open.

Weekend closures:

  • The A38(M) Aston Expressway will be closed for 7 consecutive weekends (from 8pm Fridays to 6am Mondays) – during these closures it will not be possible to get on or off the M6 at junction 6.
  • The first weekend closure will begin on Friday 14 July and the last one is due to end on Monday 28 August.
  • No traffic will be able to access the Expressway to either enter or leave Birmingham during these closures

We advise you to plan well ahead, allow more time for journeys and consider alternative modes of transport including public transport whenever possible.

Highways England Customer Contact Centre is also available 24-hours-a-day on 0300 123 5000.